Written by John Millikin, HCA Stormwater Management Committee Chair
At the May 16, 2018 Hayfield Farm HCA General Meeting, there was an update on the Hayfield Road Pipe Project. Please click on image on the left to view details in the presentation. Here are some highlights from the meeting:
- Now through September 2018, utility work continues.
- October 2018 is the possible month to break ground by Fairfax County’s (to be) selected project contractor.
- For general project issues, contact Dave Anglin (william.anglin@fairfaxcounty.gov).
- For VDOT issues, you may contact Marcus Wadsworth (marcus.wadsworth@fairfaxcounty.gov) at Lee District Supervisor Jeff McKay’s office.
- The overall project length is estimated at 12 to 14 months, though this is subject to weather and other unknown variables.
- Call Karen Sheffield, Park Manager, Huntley Meadows Park (phone 703-768-2525; email Karen.Sheffield@fairfaxcounty.gov) if you see a wood turtle in or near Hayfield Farm or Huntley Meadows. There is a picture in the power point presentation.