Announcements

Hayfield Road Pipe Project: 11/12/19

Hayfield Road Pipe Project: 11/12/19

Hayfield Road Pipe Project Update 11/12/2019

Here is an update about the Pipe Project work on Hayfield Road in the area from the Hayfield Pool to Broadmoor Street. A homeowner asked about work in that area and many residents will be interested in knowing these details.
Question
Related to the work happening in front of houses on Hayfield Road from the Hayfield Pool to Broadmoor Street, when the work on this first stretch of Hayfield Road will be completed?
Answer from County Project Managers

I will answer by what the contractor’s schedule currently says and what I think based on what I’m seeing in the field.

 

As always–please keep in mind that weather factors can influence this project. Good weather is great, of course, but bad weather can delay projects as we all know.

According to the contractor’s schedule they will be installing sanitary sewer line in advance of the start of the box culvert installation through the middle of January, 2020.

7’x4’ box culvert installation, which for our purposes also includes the outlet structure and plunge pool, will begin in mid-January, 2020. They will also be performing small water line and water service relocations as the work on the box culvert progresses. The box culvert goes up past Broadmoor St. where it changes to 48” reinforced concrete pipe (RCP). The box culvert installation should be complete by May. Installation of the 48” pipe will continue after that. The remaining work in the area of the pool will consist of restoration and repaving. According to the schedule, milling and paving happens last in October 2020.

The contractor has indicated they plan to beat the project schedule. Keep in mind they also have a hard deadline to be out of the swim club lot of May 1. They want to have most of the project work complete, except for the Telegraph Road crossing and some restoration done by then as well.

The contract substantial completion date (the date when the work is sufficiently complete so that it can be used as intended) is October 12, 2020. The contractor can always finish earlier. Punch list work should be completed within 45 days after substantial completion.

As a practice, I don’t like to predict early finishes to construction projects. I think it’s reasonable to tell the property owner that the area in front of their house will be pretty well clear of construction by mid-April at the latest, very likely several weeks earlier. Again, keep in mind that bad weather usually impacts (delays) major construction projects.

Hayfield Road Pipe Project: 11/12/19

Hayfield Road Pipe Project: 10/29/19

As many Hayfield Farm residents know, Fairfax Water repaired a water-main break on Broadmoor Street near the Hayfield Road intersection. Fairfax Water has updated our Fairfax County Stormwater Construction Branch staff. Work to provide a permanent patch over that water-main break is on their contractor’s schedule for November, so it should be completed by the end of November and with some luck, well before then.

Hayfield Road Pipe Project Contacts and Updates

Hayfield Road Pipe Project Contacts and Updates

Written by John Millikin, HCA Stormwater Management Committee Chair

Project Manager Dave Anglin hosted the Hayfield Road Pipe Project groundbreaking on September 10 at the Hayfield Pool parking lot.  Check out the talking points from John Millikin. Project work began the week of September 15 in the area behind the end of Hayfield Road near the pool parking lot. At our September 18 HCA meeting Dave provided a general project update and answered questions from residents.
Here are your contacts if you have specific questions.
  • Recommended usual contact:  John Millikin, HCA Stormwater Management Committee Chair, email John.Millikin@gmail.com, phone 703-971-5447. I will answer if I can or I will submit questions to Dave Anglin periodically and he will provide answers every 7-10 days.
  • Dave Anglin, Fairfax County Project Manager, email Dave.Anglin@fairfaxcounty.gov, phone 703-324-5500.
  • Marcus Wadsworth, Staff at Lee District Supervisor McKay’s office, email Marcus.Wadsworth@fairfaxcounty.gov, phone 703-971-6262.
  • Syed Sarwar, Garney Construction Project Manager, email ssarwar@garney.com.
Here are some useful websites:
Selected Questions & Answers from the September 18, 2019 HCA Meeting:
  • When will the project start? It started the week of September 16, 2019 with some tree-work beyond the end of Hayfield Road near the pool parking lot.
  • Are Fairfax County schools and buses aware of this project? Project Dave Anglin has worked and continues to work with Fairfax County Public Schools to ensure safety of all children and staff at our schools; he has ensured that the buses will be routed safely.
  • What are safety precautions for traffic? There will be certified flaggers who follow VDOT (Virginia Department of Transportation) safety guidelines.
  • What are project hours? Generally they follow construction hours for Fairfax County. They will generally work 7:00am to 5:00pm but may work later on some days.
  • When will the work be done at the Telegraph Road and Hayfield Road intersection? This will be done next summer 2020, when school is out.
  • What are the work hours for the intersection work?  Roadwork will occur 9:00am-3:30pm Monday through Thursday and 9:00am – 2:30pm on Friday.
  • How long will this project take? This project should be completed (weather permitting) by December 2020. For those who want a date, the contract calls for October 12, 2020 with “punch-list” items to follow. Keep in mind that there could be project changes which could extend the time for work and that weather is always a variable.