Announcements

Hayfield Road Pipe Project: Sanitary Main Installation – 11/19/2019

Hayfield Road Pipe Project: Sanitary Main Installation – 11/19/2019

Adam Jorjorian is the new Hayfield Pool Vice President and will track the Pipe Project for the Pool Board and membership. Adam asked Dave Anglin to “provide a current status of the project.” Dave copied me on his reply to Adam on November 19; Dave’s email reply is shown below.
Adam met with me (John Millikin) on Saturday November 23 for a few hours. Together we discussed the overall project history and current status and we reviewed the 100% design plans in some detail.
Here is Dave Anglin’s reply to Adam. Roughly, the new sanitary main is going to be completed before any work starts on the new storm system. I believe that the full main will be installed first, up to Bridgewater Court, then all the laterals will be connected to the new main. However, it may be the case that the pool is already connected.
The contractor scheduled 40 days for the sanitary work. So, the sanitary main and connections should be completion right after the end of the year. The contractor will then begin installing the new storm system starting with the outfall protection off the end of the roadway (at the end of Hayfield Road by the Hayfield Pool) and begin working up the hill, i.e., toward Telegraph Road. A coir log and graded level spreader are already complete just past the end of Hayfield Road near the pool. New plant installation is expected to begin any time this fall. These plants will be installed around the area disturbed off the road’s end, adjacent to the pool parking lot, and into the Park forest.
Work at the Telegraph Road intersection is required to be completed during the summer months while schools are in recess. And, the contractor is well aware they must be off the pool site with it fully restored no later than May 1, 2020. The project is scheduled to be complete in October 2020, though the contractor believes work may be complete a bit early. Of course, this is dependent on weather cooperating.
John Millikin
HCA Stormwater Management Committee Chair
Hayfield Road Pipe Project: Sanitary Main Installation – 11/19/2019

Hayfield Road Pipe Project: Preserve Two Trees; Remove One – 11/23/2019

I received this update about the Pipe Project work on Hayfield Road from Project Manager Dave Anglin on November 20. One additional tree will be removed and two will be pruned in the median strip nearest the Hayfield Pool along Hayfield Road. This work is necessary to install the storm system box culvert.

Initially, the contractor asked to remove three maples in the median strip closest to the pool – see attached marked up aerial photo. The reasons for the request are the limbs overhanging the road posing a work impediment and associated limb damage from the excavators. Dave Anglin asked two Fairfax County Landscape Architects – one of whom is an Arborist – to inspect the trees and assess the request with the goal being to save the three trees and limit any tree work to pruning, if possible. The only two circumstances to consider removing any tree are if it:

  • Were already in decline or dead; or
  • Would otherwise not survive the impact of the necessary excavation to install the box culvert.
Based on the Architect/Arborist assessment and recommendation, one tree will be removed but the other two will be preserved. The tree to be removed is shown in the attached photographs (photos are all of the same tree). This tree is in rather advanced decline and the community soon would be faced with removing it irrespective of this project. Given the poor health, it is very likely that any work close to the tree would further accelerate its death. The contractor (Garney) is required to preserve the other two maples. Garney will need to employ a professional arborist to prune the canopy limbs and to complete root pruning at a point just outside the limits of the box culvert excavation. As with the other trees removed, Fairfax County will ensure that the one removed tree will be will replaced at the project’s end.
Dave’s best guess is that this work will occur within the next few weeks, partly depending on weather of course; he will let me know once he has a better idea of when this tree work will occur.

Dave is very aware that landscaping is very important to the community and is notifying us to avoid surprising anyone. Further, in this case, this additional removal is in the best interest of all parties. Please see the four pictures with this update.

In the median closest to Hayfield Pool, three trees are circled.
Two trees will be preserved (top right and middle).
One tree will be removed (bottom left) due to poor health and severe decline.
Bark peeling/crumbling at tree’s root crown;
sign of severe decline. This is one of three pictures
all showing the same tree.
Same tree; limb scar has dry rotted completely through the limb.
The tree also bears another similar scar on the main trunk.
Third picture of same tree; similar to the previous picture;
closer to the root crown.
Hayfield Road Pipe Project: Sanitary Main Installation – 11/19/2019

Hayfield Road Pipe Project: 11/12/19

Hayfield Road Pipe Project Update 11/12/2019

Here is an update about the Pipe Project work on Hayfield Road in the area from the Hayfield Pool to Broadmoor Street. A homeowner asked about work in that area and many residents will be interested in knowing these details.
Question
Related to the work happening in front of houses on Hayfield Road from the Hayfield Pool to Broadmoor Street, when the work on this first stretch of Hayfield Road will be completed?
Answer from County Project Managers

I will answer by what the contractor’s schedule currently says and what I think based on what I’m seeing in the field.

 

As always–please keep in mind that weather factors can influence this project. Good weather is great, of course, but bad weather can delay projects as we all know.

According to the contractor’s schedule they will be installing sanitary sewer line in advance of the start of the box culvert installation through the middle of January, 2020.

7’x4’ box culvert installation, which for our purposes also includes the outlet structure and plunge pool, will begin in mid-January, 2020. They will also be performing small water line and water service relocations as the work on the box culvert progresses. The box culvert goes up past Broadmoor St. where it changes to 48” reinforced concrete pipe (RCP). The box culvert installation should be complete by May. Installation of the 48” pipe will continue after that. The remaining work in the area of the pool will consist of restoration and repaving. According to the schedule, milling and paving happens last in October 2020.

The contractor has indicated they plan to beat the project schedule. Keep in mind they also have a hard deadline to be out of the swim club lot of May 1. They want to have most of the project work complete, except for the Telegraph Road crossing and some restoration done by then as well.

The contract substantial completion date (the date when the work is sufficiently complete so that it can be used as intended) is October 12, 2020. The contractor can always finish earlier. Punch list work should be completed within 45 days after substantial completion.

As a practice, I don’t like to predict early finishes to construction projects. I think it’s reasonable to tell the property owner that the area in front of their house will be pretty well clear of construction by mid-April at the latest, very likely several weeks earlier. Again, keep in mind that bad weather usually impacts (delays) major construction projects.

Hayfield Road Pipe Project: Sanitary Main Installation – 11/19/2019

Hayfield Road Pipe Project: 10/29/19

As many Hayfield Farm residents know, Fairfax Water repaired a water-main break on Broadmoor Street near the Hayfield Road intersection. Fairfax Water has updated our Fairfax County Stormwater Construction Branch staff. Work to provide a permanent patch over that water-main break is on their contractor’s schedule for November, so it should be completed by the end of November and with some luck, well before then.